SR-60 Bridge Replacement Project
The $23 million bridge replacement project includes $10.4 million in funding from Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017. Sema Construction of Riverside, will replace three bridges along SR-60 at Pipeline Avenue, Monte Vista Avenue and Benson Avenue in San Bernardino County. The vertical clearances on these bridges are nonstandard and the structures continue to be struck by oversize vehicles, which causes significant damage. The 18-month project to replace these bridges will begin in Summer 2019, and most of the work will be completed during nighttime freeway closures.
The project is expected to be complete in fall 2021, weather permitting.
As part of the “60 Swarm”, detour signage will be in place in advance including information posted on the Caltrans overhead changeable message signs (CMS) along freeways. Motorists are advised to use alternate freeways such as I-10, I-15, SR-210 and SR-91. Access to local areas and businesses is available by accessing on and off ramps from the opposite direction of the closure.
Additional information will be released along with a press conference on July 23, 2019.
The contractor will begin nighttime work with lane closures on Monday, July 22, which will continue throughout the length of the project. Lane closures will take place from 9:00 p.m. to 5:00 a.m. The speed limit will be lowered to 55 miles per hour within the project limits.
What: Replace three bridges along SR-60.
Where: SR-60 at Pipeline Avenue, Monte Vista Avenue
and Benson Avenue in San Bernardino County.
How: Multiple, full directional freeway lane and ramp
closures from 10 p.m. Friday nights to 5 a.m.
Monday mornings. Lane closures for the duration
of the project.
When: Summer 2019 through Fall 2021
Project Cost: Sema Construction, $23 million; SB-1 funding, $10.4 million