English Springs Park Restroom Reconstruction Project
Project Description:
The work is comprised of, but is not limited to the demolition of the existing restroom, grading, preparation of a building pad and utilities for the installation of a prefabricated restroom by Public Restroom Company, Inc. (subcontractor), construction of a CMU retaining wall, and restroom perimeter concrete work.

Location:
English Springs Park at 2201 Grand Avenue.

Current Construction Activities: 
This project was awarded on June 12, 2018.  The project started on June 13, 2018, with completion expected by December 2018.

Construction Timeframe: 
120 working days

Project Contact:
Jarrod Manuel
Facilities Maintenance Supervisor
Ph: (909) 364-2793