Fairfield Ranch Road Pavement Rehabilitation
Project Description:
Work consists of repairing existing pavement, reapplying slurry seal to restore pavement condition, installation of speed and bike lane signs, and reinstalling pavement striping.

Location:
Fairfield Ranch Road between Soquel Canyon Parkway/Central Avenue to the south end of Big League Dreams Park, approximately 1.25 miles in length.


Current Construction Activities:
Work for slurry seal will take three days to complete during the week of July 10.  Pavement striping is scheduled for July 17.  The construction project is anticipated to be completed by July 21, 2017.

Construction Timeframe:
35 working days

Point of Contact:
Paul Montoya, Associate Engineer
Ph:  (909) 364-2817


Site Plan