Project Description:
The work comprises, but is not limited to: mobilization, traffic control, clearing and grubbing, earthwork and grading, removal of existing AC curb/dike, PCC curb, sidewalk, driveway aprons, walls, fences, sod, trees and vegetation, cold milling existing AC pavement; relocation of existing fence/gate, relocation of traffic sign/post; adjustment of utility vault/box, manhole frame and cover; construction of PCC sidewalk, PCC driveway aprons, curb and gutter, curb drain, retaining wall/curb, curb ramps, cross-gutter, AC pavement overlay; signing and striping, street light conduits, conductors, lights and pull boxes, and other related work.

Location:
Street Improvements:
South Side of Gird Avenue between Pipeline Avenue and Del Norte Avenue
South Side of Lugo Avenue between Pipeline Avenue and Del Norte Avenue
South Side of El Molino Boulevard between Pipeline Avenue and Montecito Drive

Trail Improvements:
Val Verde Street right of way between Gird Avenue and Country Club Drive

Current Construction Activities:
Eleven bids were received and opened on July 25, 2019.  The apparent low bidder was Roadway Engineering and Contracting, Inc. from Mira Loma at $768,208.00.  City Council awarded the bid to Roadway at their meeting of August 13, 2019.  The contractor was notified and a pre-construction meeting was held on August 29, 2019.  The contractor began providing the Construction Schedule, the proposed Traffic Control Plan and the SWPPP for this construction.  Pending City approval of the SWPPP, construction will begin the week of September 16, 2019.  The project completion time is 60 working days, with a final completion date of December 11, 2019.

Construction Timeframe:
60 working days

Point of Contact:
Mark Raab, Senior Engineer
Ph:  (909) 364-2746