FY 2018-19 Street Improvement Project
Project Description:
The work comprises, but is not limited to: Mobilization; Traffic Control; selective 2-inch grind and 2-inch AC overlay; 1.5-inch full-width grind and overlay; crack seal; application of Type 1 conventional slurry; and restoration of striping, pavement markings, and legends.

Depending on the existing condition and needs of a street, the repair work may consist of the following:

1. Removal by grinding small pavement sections and overlaying deteriorated asphalt pavement (patch work);
2. Removal by grinding full-width sections and overlaying asphalt pavement;
3. Crack sealing; and
4. Slurry sealing over the entire pavement.

Slurry sealing is a preventative maintenance process that is designed to prolong the life of the asphalt surface and avoid the development of potholes.
               
Location:      
Laband Village Residential Area, Monteverde Drive Residential Area, La Sierra/ Madrugada Drive Residential Area, Silver Ridge Road Residential Area, Alterra Park Residential Area, Carriage Hills Lane Residential Area, Los Serranos Residential Area, Eucalyptus Avenue Adjacent to Community Park.


Current Construction Activities: 
  • The construction contract was awarded to Onyx Paving Company, Inc. on April 9, 2019; 
  • Construction is scheduled to start on Monday, May 6, 2019, and is anticipated to be completed early August 2019.  View the Construction Project Schedule Update and Site Map.

 Please note the following advice during construction:

  1. Project work area includes several neighborhoods with the City limits and various phases of repair work will be done accordingly;
  2. “No Parking” signs will be posted on particular streets at least 48 hours in advance prior to the scheduled work;
  3. Work hours will be limited to 7:00 AM to 3:30 PM (unless the Contractor still needs to allow the pavement or slurry seal to dry completely prior to opening to vehicular traffic);
  4. “Door Hangers” will be distributed at least 48 hours in advance at those areas/streets receiving slurry seal treatment; and
  5. Residents are advised to park their vehicles outside the repair work limits if they plan to travel during the construction work.

Construction Timeframe:
60 working days

Project Contact:
Fe Rama, Senior Engineer
Ph:  (909) 364-2776


Site Map