Pavement Project on Pipeline Avenue Starts May 11

road work ahead sign

The City of Chino Hills pavement project on Pipeline Avenue from Chino Hills Parkway south to Glen Ridge Drive will begin on May 11. Work hours are 7:00 am to 4:00 pm on weekdays. Traffic will be directed through the project area at times.  Message boards were placed to notify the public. The pavement will be ground down two inches and a two-inch overlay applied. A catch basin will be reconstructed to remove a depression in the road. The schedule calls for completion of the project by the end of June. The $220,000 project was awarded to All American Asphalt, with funding provided by Community Facilities District 5.