Traffic Signal Modification at Boys Republic Drive and City Hall Parking Lot

Project Description:

The work comprises, but is not limited to: mobilization, traffic control, removal and construction of ADA access ramp, island passageway, sidewalk, curb and gutter, cross gutter and spandrel; construction of decorative crosswalk; cold mill and asphalt concrete overlay; installation of pedestrian hybrid beacons, pedestrian heads, and necessary appurtenances; adjustment of manhole; restoration of pavement markings, raised markers and striping; and other necessary work to complete the traffic signal modification and street improvements. 

Notice of Exemption, Filed April 27, 2023

Location:

Boys Republic Drive at City Hall Parking Lot.

Location Map

Current Construction Activities:  

Prospective bids were submitted by June 22, 2023.  The project was awarded to California Professional Engineering on September 26, 2023. 

Construction is anticipated to begin in October 2023 and is anticipated to be completed by April 2024.

Construction Timeframe: 

120 working days