Saddle Replacement - Phase 3

Project Description:

The Work comprises, but is not limited to: mobilization, traffic control, providing construction phasing schedule, residential notifications, potholing, saw-cutting and removal of pavement, sheeting/shoring, exposing the existing PVC water main, lateral and saddle, replacing saddles and corporation stops, reconnecting existing water service laterals, trench restoration; 

Street improvements which includes: 5-ft Tapered Grind and AC overlay, crack seal, application of Type I conventional slurry seal, adjust existing utility manholes and water valve can to final grade, restoration of speed hump, and restoration of striping, pavement markings, and legends.

Location:

Live Oak Rd, Sonrisa Residential, Madrugada Drive Residential.

Current Construction Activities:  

Construction started the week of August 1, 2022 and is tentatively slated to be completed in November 2022 (weather permitting).

The first area of work is the Madrugada Drive residential area, which will go through the end of September.  Affected residents will temporarily have their water shut off during the saddle replacement. Door hangers will be provided at least 48 hours before water shut-off. Please refer to the Construction Schedule exact dates and location for the water shut-off.

Construction Schedule

*FOR SPECIFIC DATE AND TIME FOR A WATER SHUT OFF, PLEASE REFER TO DISTRIBUTED DOOR HANGER.

Construction Timeframe: 

90 working days

Project Contact:  

Fe Rama, Senior Engineer
Phone: 909-364-2776
frama@chinohills.org

Nicole Seo, Assistant Engineer
Phone: 909-364-2755
nseo@chinohills.org 

Site Plan