Maroon Bell - Winchester Water Main Replacement Project

Project Description:

The work comprises, but is not limited to: Mobilization; traffic control; installation of approximately 3,900 LF of 8-inch PVC C900 DR 14 pipe, including gate valves, fixtures, appurtenances, thrust blocks, blow off, and air vac assemblies, and removal of portions of existing pipe.  In addition, the work consists of installation of 111 EA 1-inch copper water service laterals and connecting to existing meters; installation of fire hydrants and valve assemblies, abandon-in-place existing water mains, pressure testing, disinfection, BacTs; trenching and pavement restoration, crack seal, slurry seal application, replacement of concrete cross gutter, speed hump, and restoration of pavement markings, raised markers, and striping; and other necessary work to complete the water replacement and street improvements.

Notice of Exemption - Filed July 12, 2023

Location:

Ashcroft Court
Copper Saddle Way
Gold Dust Way
Maroon Bell Road
Prospector Lane
Redstone Court
Stetson Way
Telluride Drive
Winchester Way

Current Construction Activities:

Bid Opening was on August 17, 2023.  
The project was awarded to All Cities Engineering on September 26, 2023.
Construction commenced on January 4, 2024.

Most of the main line, services, and appurtenances have been installed.  The main line will soon undergo testing.  Upon successful test results, the main will connect to existing water main which will require temporary shutdown.  Affected residents will be notified in advance to minimize any inconveniences.

Estimated completion is mid-May 2024.

Location Map

Construction Timeframe: 

95 working days

Point of Contact:

Fe Rama, Senior Engineer
Phone: (909) 364-2776
Email: frama@chinohills.org

Danny Hernandez, Associate Engineer
Phone: (909) 364-2760
Email: dhernandez@chinohills.org