Grand Avenue Pavement Rehabilitation Project

Project Description:

Mobilization; Traffic Control; removal and reconstruction of deteriorated pavement, 2-inches grind and overlay asphalt pavement; reconstruction of access ramps; adjustment of water valves, sewer manholes and utility covers; installation of video detection; and restoration of striping, pavement markings, and legends. Work will be required to be performed at night.

Location:

Grand Avenue from Peyton Drive to State Route 71.

Current Construction Activities:

The project was awarded to R. J. Noble Company on July 13, 2021 and started in January 2022.  Video detection and concrete work was completed in February.  The contractor will grind and overlay the paving which will occur during the night from 8:30 p.m. to 5:00 a.m. in April 2022.

Construction Timeframe: 

30 working days

Point of Contact:

Carl Hassel, Sr. Engineer
Phone: 909-364-2817
Email: chassel@chinohills.org