Founders Drive Pavement Rehabilitation Projet

Project Description:

The work comprises, but is not limited to: Mobilization; Traffic Control; selective 1.5-inch grind and 1.5-inch AC overlay; ADA Ramps, adjustment of existing manholes to grade; adjustment of water valve can covers; installation of video detection, and restoration of striping, pavement markings, and legends.

Location:

Founders Drive from Grand Avenue to Chino Hills Parkway. 

Current Construction Activities:

This project will begin on Tuesday, August 10, 2021.  The contractor will start with concrete work during the first week.  The following week the contractor will grind the roadway, do the full depth removals and then overlay the roadway.

One lane of traffic will be open at all times and minor delays will occur.  There will be no street parking during the paving operations.  The contractor will be placing changeable message signs before the project begins and door hangers will be provided prior to the start of work.

Construction Timeframe: 

20 working days

Point of Contact:

Carl Hassel, Sr. Engineer
Phone: 909-364-2817
Email: chassel@chinohills.org