Chino Avenue Pavement Rehab

Project Description:

The work comprises, but is not limited to: Mobilization; Traffic Control; selective 2-inch grind and 2-inch AC overlay; ADA Ramps, adjustment of existing manholes to grade; adjustment of water valve can covers; installation of video detection, and restoration of striping, pavement markings, and legends.  

Location:

Chino Avenue from Peyton Drive to State Route 71.

Current Construction Activities:

Bids were opened on April 22, 2021. The anticipated award date is June 8, 2021.

Construction Timeframe: 

30 working days

Point of Contact:

Carl Hassel, Sr. Engineer
Phone: 909-364-2817