Mystic Canyon Drive Pavement Rehabilitation

Project Description:

The work consists of, but is not limited to: mobilization; traffic control, cold milling of existing AC pavement; AC overlay; upgrading existing P.C.C. access ramps where needed to comply with current ADA standards; adjustment of valves and manholes to grade, and roadway pavement signing and striping.

Location:

Mystic Canyon Drive from Butterfield Ranch Road to Shady View Drive.  

Current Construction Activities:

Bids were opened on March 26, 2020, and the project was awarded to Onyx Paving Inc. on April 28, 2020.  Work will begin on May 26 and be completed in July.

Construction Timeframe: 

40 working days

Point of Contact:

Carl Hassel, Sr. Engineer
Phone: 909-364-2817
Email: chassel@chinohills.org