Pipeline Avenue (Chino Hills Parkway to Glen Ridge) Pavement Rehabilitation

Project Description:

The Work comprises, but is not limited to:  Mobilization; Traffic Control; full-width street 2-inch grind and 2-inch AC overlay; local depression reconstruction, adjustment of utility manholes, water valves and covers; restoration of striping, pavement markings, and legends.  

Location:

Pipeline Avenue from Chino Hills Parkway to Glen Ridge Drive.

Current Construction Activities:  

Bids were opened on January 23, 2020, with an anticipated award of construction on February 25, 2020.  

Construction Timeframe:

25 working days

Project Contact:

Carl Hassel, Sr. Engineer
Ph:  909-364-2817
chassel@chinohills.org