Pipeline Avenue (Chino Hills Parkway to Glen Ridge) Pavement Rehabilitation

Project Description:

The Work comprises, but is not limited to:  Mobilization; Traffic Control; full-width street 2-inch grind and 2-inch AC overlay; local depression reconstruction, adjustment of utility manholes, water valves and covers; restoration of striping, pavement markings, and legends.  

Location:

Pipeline Avenue from Chino Hills Parkway to Glen Ridge Drive.

Current Construction Activities:  

Construction began on May 11, 2020.  Work hours are from 7:00 a.m. to 4:00 p.m. on weekdays.  Traffic will be directed through the project area at times.  Message boards were placed to notify the public.  The pavement will be ground down two inches and a two-inch overlay applied.  A catch basin will be reconstructed to remove a depression in the road.  The schedule calls for completion of the project by the end of June.

Construction Timeframe:

25 working days

Project Contact:

Carl Hassel, Sr. Engineer
Ph:  909-364-2817
chassel@chinohills.org