Slate Drive Pavement Rehabilitation

Project Description:


The work comprises, but is not limited to:  Mobilization; Traffic Control; full-width street 2-inch grind and 2-inch AC overlay; reconstruction of access ramp; adjustment of utility manholes, water valves and covers; restoration of striping, pavement markings, and legends.

Location:


Slate Drive between Soquel Canyon Parkway to Butterfield Ranch Road.   

Current Construction Activities:


This project is currently out to bid.  The bids are scheduled to be opened on December 19, 2019 with an anticipated award of construction on February 11, 2020.
       

Construction Timeframe:

  
40 working days


Point of Contact:


Carl Hassel, Sr. Engineer
Ph:  909-364-2817