Project Description:


The work comprises but is not limited to:  Mobilization; Traffic Control; selective 2-inch grind and 2-inch AC overlay; ADA Ramps, adjustment of existing manholes to grade; adjustment of water valve can covers; storm drain culvert replacement (2) regrading of shoulders and placement of compacted base material, and restoration of striping, pavement markings, and legends.  

Location:


Woodview Road between Peyton Drive and 2000' West of Pipeline Avenue.


Current Construction Activities:
 


The bid was opened on July 14, 2022 with an anticipated award of construction on September 13, 2022.  Work is anticipated to begin in October 2022.
 

Construction Timeframe:


35 working days