Pine Avenue Pavement Rehabilitation

Project Description:


The work comprises a grind and overlay of the roadway. Manholes and valves will be adjusted to the new roadway surface. Striping will be restored. The intersection of Butterfield Ranch Road and Pine Avenue will have video detection installed.

Location:


Pine Avenue between SR 71 and Butterfield Ranch Road 


Current Construction Activities:
 


This project was awarded on 11/26/19.  Field work is anticipated to begin in February.
 

Construction Timeframe:


20 working days


Project Contact:


Carl Hassel, Sr. Engineer
Ph:  909-364-2817