The Work comprises, but is not limited to: mobilization; traffic control; clearing and grubbing, earthwork, excavation and grading; removal and disposal of unclassified material, sod, trees, vegetation, existing ac, concrete pavement, curb & gutter, brick, block or wood pilaster, block wall, chain link and wood fences; relocation of traffic sign/posts and mail boxes, water meters, fire hydrants; adjustment of utility vault/boxes, manhole frames and covers; construction of PCC sidewalks, PCC driveway aprons, PCC curb and gutter, curb drains, retaining walls, PCC curb ramps, PCC cross-gutters; site grading, rock embankment and slope toe protection, and decomposed granite (DG) paths; AC pavement overlay; restore landscaping and irrigation, signing and striping; installation of street light fixtures, conduits, service meter pedestals, pull boxes, and all other relative work.
Valle Vista Drive between Del Norte Avenue to Descanso Drive; Gird Avenue between Del Norte Avenue to Valle Vista Drive; Lugo Avenue between Del Norte Avenue to Valle Vista Drive.
The bid opening was on December 22, 2021, and the project was awarded on January 25, 2022. The project began in early March and will be completed in July 2022.
60 working days
Carl Hassel, Senior Engineer
Phone: 909-364-2817