Los Serranos Infrastructure Improvements – Safe Routes to School (West) – Project No. S19005

Project Description:

The work comprises, but is not limited to: mobilization, traffic control, clearing and grubbing, earthwork and grading, removal of existing AC curb/dike, PCC curb, sidewalk, driveway aprons, walls, fences, sod, trees and vegetation, cold milling existing AC pavement; relocation of existing fence/gate, relocation of traffic sign/post; adjustment of utility vault/box, manhole frame and cover; construction of PCC sidewalk, PCC driveway aprons, curb and gutter, curb drain, retaining wall/curb, curb ramps, cross-gutter, AC pavement overlay; signing and striping, street light conduits, conductors, lights and pull boxes, and other related work.

Location:

Street Improvements:
South Side of Gird Avenue between Pipeline Avenue and Del Norte Avenue
South Side of Lugo Avenue between Pipeline Avenue and Del Norte Avenue
South Side of El Molino Boulevard between Pipeline Avenue and Montecito Drive

Trail Improvements:
Val Verde Street right of way between Gird Avenue and Country Club Drive

Current Construction Activities:

This project is nearing completion, with all three streets paved with new asphalt, curb, gutter, concrete sidewalk and new concrete driveways.  The contractor is also finishing up the grading work within the walking path and plans to install the decomposed granite walking surface within the next two weeks.

As soon as the Edison work orders have been issued, the street lights will be installed and the electric wiring connected. 

Construction Timeframe:

60 working days

Point of Contact:

Mark Raab, Senior Engineer
Phone: 909-364-2746
mraab@chinohills.org