Grand Avenue Pavement Rehabilitation
Description:
Full width grind and AC overlay project.

Location:
 
Grand Avenue - between Peyton Drive and Chino Hills Parkway.

Current Construction Activities:

Authorization to bid is scheduled to be approved by Council on December 9, 2014.  Bid opening is scheduled for January 15, 2015, with an anticipated award of contract on January 28, 2015.  Estimated construction to begin in mid March 2015.

Construction Timeframe:  2 months.

Project Contact:

Anne Dutrey, Senior Engineer
Ph:  (909) 364-2760